Warringtonfire’s new laboratory hits commissioning stage

Latest News Wed, Apr 17, 2024 8:26 AM

Warringtonfire’s new $30m laboratory at Birchwood Technology Park is now at the ‘third fix’ stage, with four out of a planned seven of its state-of-the-art fire resistance testing furnaces already installed, marking significant progress towards its completion and commissioning.

In August 2023, Warringtonfire, the UK’s leading testing and certification provider, announced it was building a brand new 101,000sqft facility.

This significant investment enables Warringtonfire, part of the global Element Materials Technology (Element) group, to expand capacity and meet increasing demand for fire resistance testing of critical fire safety products and systems, such as fire doorsets, intumescent coatings for steel protection, and other passive fire protection solutions.

Ten months into Warringtonfire’s projected 17-month build programme, four furnaces have been fitted and are ready to enter the commissioning phase shortly. The furnaces will be supported by a raft of technology to carefully manage air quality both during and after the testing process.

This includes new air handling and high-performance ventilation systems, as well as cold smoke and hot smoke extraction systems, ensuring a better working environment for employees and compliance with strict environmental regulations. To support this, specialists from Element undertook an extensive Environmental Impact Assessment (EIA) involving acoustics and noise modelling, air quality dispersion modelling, and emissions monitoring.

By the laboratory’s open date, scheduled for January 2025, two vertical furnaces, two horizontal furnaces, and one indicative furnace will be ready to accept test specimens. Another two furnaces, one horizontal and one vertical, will be installed by the end of 2026. In total, this will represent an 80% increase in testing capacity over Warringtonfire’s current site at Holmesfield Road, Warrington. Following the opening of the Birchwood Park laboratory, the existing facility will become a centre of excellence for reaction to fire testing, which are smaller scale tests including spread of flame and heat release.

Dafydd Llewelyn-Jones, Project Manager for Element Materials Technology, has been coordinating the laboratory’s construction: “We are on track with our progress and are actually seven weeks ahead of schedule in terms of the furnaces themselves. We are now moving swiftly along to fitting out all the office areas and control rooms, commissioning the building services, and completing the test bay preparation areas.

“It is brilliant to see this project coming together. We have put a significant amount of money into making this new laboratory truly one of the best in Europe, if not the world.”

Besides the investment into furnaces, Warringtonfire is committed to reducing the laboratory’s carbon footprint and making the new site as sustainable as possible. Measures include energy-efficient fans, upgraded power supply transformers that consume minimal electricity when idle, and electric vehicle (EV) infrastructure including a fleet of EV forklifts and charging points.

The site will also be well lit, through a combination of natural light from skylights and LED lighting that delivers a high lux level. In addition, the laboratory is set up to accept a blend of clean hydrogen and natural gas once local infrastructure offers this service.

Leigh Hill, Director, Built Environment Europe, commented: “Our new laboratory will be the largest state-of-the-art fire testing and certification facility worldwide, and one of the most environmentally conscious too. We have made substantial investments in procuring the most cutting-edge building service equipment available today, reinforcing our position as industry leader and ensuring sustainable operation for years to come.”

Featured News

Specification news
Construction launches skills mission at leaders meeting

Senior leaders from across construction and Government Ministers have launched the...

Read More >>

Specification news
Data centre boom fuelling building services growth

Building services contractors are increasingly taking the lead on data centre...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Amtico Bio Support Document  Brochure

Amtico Bio Support D...
By Amtico

Download Now >>

Amtico Access Brochure

Amtico Access
By Amtico

Download Now >>

Amtico Acoustic Brochure

Amtico Acoustic
By Amtico

Download Now >>

Amtico Click Smart Brochure

Amtico Click Smart
By Amtico

Download Now >>

Amtico Decor Brochure

Amtico Decor
By Amtico

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Hardie® Plank
Hardie® Plank

James Hardie fibre cement products are built to last. It's the go to façade for builders,...

Read More >>

Hardie® Panel

With James Hardie, It’s Possible™If you're looking for a high performance, A2 fire-rated façade...

Read More >>

Hardie® Backer
Hardie® Backer

With James Hardie, It’s Possible™Moisture sensitive areas like kitchens and bathrooms are...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Mira Vista Heatloop
Mira Vista Heatloop

Mira Showers is delighted to introduce the new Mira Vista HeatloopTM – an innovative and stylish...

Watch Now >>

Why our Canopies Last Longer
Why our Canopies Last Longer

https://www.aandslandscape.co.uk/ Find out why A&S Landscape Canopies last longer than alternatives....

Watch Now >>

Enclosed Dining Canopy - Hampton Gardens School
Enclosed Dining Canopy - Hampton Gardens School

A&S Landscape designed and installed a large enclosed, curved roof canopy for Hampton Gardens School...

Watch Now >>