TPS to complete Guernsey Airport upgrade early

Hotel, Sport & Leisure Tue, Mar 22, 2016 5:25 PM

TPS to complete Guernsey Airport upgrade early

Guernsey’s £80m Airport 2040 upgrade is set to complete two months ahead of schedule with a little help from the heat wave enjoyed by the British Isles this summer.

Originally planned to take 22 months and finish by the end of 2013, the works are likely to be completed this October.

Design and engineering specialist TPS, part of the Carillion group, has project managed the rehabilitation and improvement of runway, taxiways and aircraft aprons at the airport. This has necessitated the import of 220,000 tonnes of granite and limestone aggregates from the UK to the island, supplementing 100,000 tonnes of locally quarried stone.

Under the watchful eye of TPS’ client project manager Gerry Prickett, this essential maintenance and improvement work has included the removal of an historic dip in the runway, the construction of an additional 120 metre runway section and the complete reconstruction of Guernsey Airport’s apron area.

Work began in earnest in March 2012, and shortly after the airport closed for two days to enable the reconstruction of large sections of the runway’s outer edges. The main asphalt operation started in July of that year, with the infill of the dip at the western end of the site. This had been a feature of the runway since it was first constructed more than 50 years ago, but it no longer met modern safety standards. The operation involved contractors working at night to build up the levels in the section with successive layers of asphalt.  Over ten weeks, more than 45,000 tonnes of asphalt was used to raise the height of the runway by up to 1.6 metres.  

Since then, similar works have been carried out elsewhere on the runway to improve its strength and previously undulating profile.  Once complete, this enabled contractor Lagan to lay the final top course. This is done after the airport closes each night, and involves laying new asphalt and then cutting grooves in the surface to enable water to quickly drain off. Having started at the western end, the work moves eastwards along the full length of the runway.

“The new section of runway added at the western end of the site moves the airstrip 120 metres to the west, while the existing taxiway also had to be extended to link the western end with the rest of the airfield,” reveals Prickett. “The new runway maintains its existing operational length of 1,463 metres but this shift provides longer safety areas at both ends of the runway.”

The other key part of the project sees the apron, the aircraft hardstanding beside the terminal where passengers and crew board and disembark the aircraft, undergo a full rebuild.  “Although Guernsey Airport’s new terminal was built in 2004, the old apron dating back to the 1960s was retained and bore the wear and tear from 50 years of trafficking,” explains Prickett. The apron works have seen all the old concrete crushed and re-used for the foundations of the renewed area.

To maintain normal airport operations the work has been carried out in six phases, with two of these phases providing additional aircraft stands on what were grass areas.  The final major phase this summer involved the bussing of passengers to and from these areas whilst a large part of the existing concrete was re-built to higher strength. As the majority of this construction has taken place during the day, it has been clearly visible to passengers using the terminal.

In addition TPS is carrying out work on the airport’s new drainage system, the installation of new navigational aids, a complete replacement of the airfield ground lighting and the installation of head of stand services. TPS are the design engineers for the latter, having designed the fixed electrical ground power systems for aircraft to connect to when on the apron, and the stand number indicator systems that identify the aircraft parking positions.  

While the weather has helped the contractors this summer, it hasn’t always been on their side. The work was significantly hampered by the wettest twelve months on record in 2012, followed in March 2013 by Guernsey’s heaviest snowfall in 30 years and the overall affect was to put the project about 8 weeks behind programme. However, the dry weather and glorious sunshine of the last few months has meant almost no lost shifts and much improved ground conditions for drainage and apron re-construction works.  This has seen the completion of runway works on 10th August, with the remainder of the works now set to complete two months early.

Featured News

Specification news
Hotel specifies Dorma Huppe moveable walls

Partitioning expert, Style was recently contracted to work with architects, Jestico &...

Read More >>

Specification news
Nelson Place enhances its student facilities with...

The Nelson Place development in Belfast, the city’s largest purpose-built student...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Proctors Spacetherm Building & Construction Brochure

Proctors Spacetherm...
By A Proctor Group Ltd.

Download Now >>

Proctors Proctor Passive Brochure

Proctors Proctor Pas...
By A Proctor Group Ltd.

Download Now >>

Proctors Air Brochure Brochure

Proctors Air Brochur...
By A Proctor Group Ltd.

Download Now >>

Proctors Modular & Offsite Solutions Brochure

Proctors Modular & O...
By A Proctor Group Ltd.

Download Now >>

Proctors Hamm Principles Brochure

Proctors Hamm Princi...
By A Proctor Group Ltd.

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

SOPRALENE FLAM 180 AF
SOPRALENE FLAM 180 AF

Membrane composed of elastomer modified bitumen and a non woven polyester reinforcement.The upper...

Read More >>

FLAGON SR DE PVC
FLAGON SR DE PVC

Membrane composed of flexible PVC and a polyester reinforcement. Available in different RAL...

Read More >>

FLAGON S PVC
FLAGON S PVC

Membrane composed of flexible PVC. Available in different RAL Colours.Used for detailing work. The...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Why our Canopies Last Longer
Why our Canopies Last Longer

https://www.aandslandscape.co.uk/ Find out why A&S Landscape Canopies last longer than alternatives....

Watch Now >>

Enclosed Dining Canopy - Hampton Gardens School
Enclosed Dining Canopy - Hampton Gardens School

A&S Landscape designed and installed a large enclosed, curved roof canopy for Hampton Gardens School...

Watch Now >>

Dining Area Canopy at John Spendluffe Technology College
Dining Area Canopy at John Spendluffe Technology College

We designed and installed a new dining area canopy for John Spendluffe Technology College. This has...

Watch Now >>