Flagship velodrome gets innovative HVAC solution

Hotel, Sport & Leisure Tue, Mar 22, 2016 5:01 PM

Flagship velodrome gets innovative HVAC solution

Glasgow’s £95 million 5000-seat Commonwealth Sports Arena and adjacent 2000-seat Sir Chris Hoy Velodrome are a world-class facility that will be used as competition venues for the 2014 Commonwealth Games.  

SPIE Matthew Hall provided all the HVAC piping services including low temperature hot water, chilled water and domestic hot and cold water.

The large-scale project comprised a chilled water plantroom and boilerhouse, housing a total of 19 pumps, and several kilometers of distribution pipework.   

To meet the demanding construction schedule the contractor needed a reliable system that was quick and easy to install.

The complexity of the project also made it essential to accommodate design changes quickly and easily.  Lack of space in the mechanical rooms – both for plant and for people to work - was a key constraint: the need to install large plant into confined spaces called for the elimination of cumbersome pipework and fittings, and for as much work as possible to be done off site.

The solution was to change from the original specification for standard welding and flanging to grooved technology and prefabricate in a bespoke off-site centre.  Engineering services were installed using a range of Victaulic rigid and flexible couplings, valves, strainers, mechanical tees and elbows on BS1387 steel pipe from 65mm – 500mm in diameter. 

Up to 95% of the entire installation was prefabricated off site and delivered as and when needed on the jobsite.  This included pipe spools and pre-assembled modules for the boiler room and chiller room, all the risers and the main pipe runs from the risers to the floors.    

Tightness of space in the energy centres was overcome by using grooved components to replace bulky welded/flanged items and cut down the amount of pipework required.  Pumps and chiller units were pre-assembled with valves and fittings in the prefabrication shop. 

The use of butterfly valves saved weight, whilst the facility to close-couple valves reduced the number of pipe spools needed, and the potential for joint leaks.

To reduce noise and vibration, three flexible couplings were installed on either side of each pump and chiller in place of traditional rubber bellows.  Small and light but with high integral strength for maximum reliability, the couplings not only saved space but dramatically reduced installation time.   

SPIE Mathew Hall Construction Manager, Gary Walker, explained: “Comparing welding and flanging with the grooved system is like comparing chalk and cheese.  When you’ve got 20 welds per pump and 20 flanges with multiple nuts and bolts compared with a Victaulic coupling with just two nuts and bolts it’s a big difference. 

"A 100mm weld might take one and a half to two hours to complete but a Victaulic joint can be made in minutes.  And when you’ve got a 450mm pipe that might take five hours to weld you can cut, groove and fit a Victaulic joint in around two hours. I wouldn’t contemplate doing a job like this using anything other than Victaulic.”  

There was a substantial saving by not having to purchase rubber bellows. Avoiding complex bracketry which is needed to support pipework on top of bellows was an added factor in reducing cost, time and footprint.  

“Rubber bellows are perishable and need replacing but the main advantage with grooved modules is that they’re easier to build off as you don’t need brackets to compensate for the movement  of the bellows,” Walker commented.  

Where possible, the contractor used ‘installation-ready’ couplings which forms a strong, reliable joint without the need to disassemble and reassemble bolts, nuts, gasket and housings.  With no loose parts to drop or mislay, they made work on the jobsite quicker and more efficient. 

“All the couplings were quick and easy to use but the installation-ready 177s were at least twice as quick to install so that sped up the programme even more,” said Walker.   

The project successfully met a set of challenging criteria to achieve a fit-for-purpose solution on time and on budget. 

“The installation was completed in around half the time it would have taken to weld and it was three times as quick to flush the non-welded system. We saved 25 – 30% on total installed costs compared with traditional methods,” said Senior Project Manager, Brian Fee.

“Space was at a premium and we were able to use Victaulic products for everything, including work in confined spaces and tight angles where we couldn’t have welded.  The flexibility of the fittings made a big difference.”  

A flagship project for SPIE Mathew Hall in the UK, the installation has not only convinced the team to tackle similar projects in the same way but has also attracted the attention of SPIE in France. 

It is an excellent example of the benefits of taking a non-traditional approach: using grooved-end pipe-joining systems in preference to welding and flanging, combined with extensive prefabrication. 

At a time when quality, cost and delivery are key criteria for construction projects, the project signals the way forward for greater efficiencies through this approach.   

Featured News

Specification news
TRANSFORMING HOTEL AND LEISURE FACILITIES WITH ZEST...

Bathrooms, showers, and changing rooms within hotels and sports and leisure...

Read More >>

Specification news
Senior brings light and shade to new hotel scheme

Dual coloured and slim framed aluminium fenestration solutions from Senior...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Novantica - Cement Free Restoration  Brochure

Novantica - Cement F...
By Fassa Bortolo

Download Now >>

Fassatherm System - Product Catalogue  Brochure

Fassatherm System -...
By Fassa Bortolo

Download Now >>

Fassarend System - Product Catalogue  Brochure

Fassarend System - P...
By Fassa Bortolo

Download Now >>

Fassalime System - Product Catalogue  Brochure

Fassalime System - P...
By Fassa Bortolo

Download Now >>

Sport England’s Performance Archery Centre Brochure

Sport England’s Perf...
By Passivent

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Straightcurve®
Straightcurve®

Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...

Read More >>

RLG600 Access Flooring System
RLG600 Access Flooring System

The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...

Read More >>

RHG600 Simploc
RHG600 Simploc

Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Discover the first-ever reference book for stone wool insulated sandwich panels
Discover the first-ever reference book for stone wool insulated sandwich panels

“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...

Watch Now >>

Portakabin | Installation at the iconic Admiralty Arch, London
Portakabin | Installation at the iconic Admiralty Arch, London

Portakabin | Installation at the iconic Admiralty Arch, London

Watch Now >>