Building Safety Regulator delays unacceptable says Lords Committee

Latest News Thu, Dec 11, 2025 9:29 AM

A cross-party House of Lords Committee has warned the Government that “unacceptable” delays caused by the Building Safety Regulator’s (BSR) approval processes is leaving residents waiting for remediation of dangerous cladding in unsafe buildings and increasing costs for leaseholders.

Whilst welcoming the increased scrutiny the Building Safety Regulator has brought to the design, construction and management of buildings in the interest of safety, the Industry and Regulators Committee’s report The Building Safety Regulator: Building a better regulator, published today also warns that the delays mean the Government is in danger of missing its target to build 1.5 million homes by 2029.

Whilst welcoming the increased scrutiny the Building Safety Regulator has brought to the design, construction and management of buildings in the interest of safety, the Industry and Regulators Committee’s report The Building Safety Regulator: Building a better regulator also warns that the delays mean the Government is in danger of missing its target to build 1.5 million homes by 2029.

After hearing from a range of witnesses including representatives of campaign groups and other organisations, developers, housing associations and regulators which work closely with the BSR, the Committee also found:

  • The BSR has not given clear enough guidance on how applicants are supposed to demonstrate that their buildings are safe;
  • Many applications are being rejected or delayed due to basic errors and applicants’ inability to evidence how they are considering elements of fire and structural safety, which reflects poorly on the construction industry;
  • Many construction products do not have relevant product standards, leaving them entirely unregulated;
  • Difficulties in local authority funding and the introduction of regulation have left an ageing workforce of building inspectors who are struggling to meet demand;
  • Despite these skills shortages, smaller works such as bathroom renovations in high-rise buildings are being subject to the scrutiny of the BSR’s hard-pressed multidisciplinary teams.

As a result, the report is calling on:

  • The BSR to give greater guidance to its MDTs on how compliance with the Building Regulations should be evidenced and assessed to ensure greater consistency;
  • The Government to remove smaller works from the BSR’s building control approval processes, or introduce a streamlined approval process for them;
  • The BSR to allocate the same MDTs to similar buildings or projects built by the same organisation, which could improve efficiency and consistency;
  • The Government to provide long-term funding for the training of new building and fire inspectors.

Chair of the Committee Baroness Taylor of Bolton said: “The tragic loss of 72 lives at the Grenfell Tower fire laid bare the urgent need to reform building safety regulation in England, particularly for high-rise buildings. The introduction of the Building Safety Regulator was a necessary and welcome step.

“However, the scale of the delays caused by the BSR has stretched far beyond the regulator's statutory timelines for building control decisions. This is unacceptable. We welcome that the Government and the BSR are now acting to try and make practical improvements, but this will not address the anxiety and frustration that residents and companies have experienced.

“It does not improve safety to delay vital remediation and refurbishments, nor to deter the delivery of new housing in high-rise buildings. We expect to see further action from the Government and the BSR to ensure that construction projects in high-rise buildings can be brought forward more quickly, without compromising on vital safety improvements.”

In a statement, the BSR said: "We recognise that building control applications have been taking too long to process.

“Since the Committee began its hearings in the summer, we have made significant changes to speed up decision making with a focus on new build and cladding remediation applications. These include a new Innovation Unit, batching processes, and the introduction of account managers to improve communication with applicants.

“These improvements are helping to increase industry confidence and, in the 12 weeks to 24 November, enabled construction to proceed on over 11,000 new homes. We also saw a 73% approval rate for new build decisions during that time, demonstrating that changes introduced are beginning to work.

“Making sure buildings with dangerous cladding are remediated quickly is also a priority and will be the focus of our new Remediation Enforcement Unit which will begin working on cases in the new year.

"The Committee’s recognition that BSR has successfully driven a ‘crucial cultural shift’ toward safer homes is a welcome endorsement of the new regime.

“We remain firmly committed to being a proportionate and enabling regulator that works alongside the construction sector to protect residents and deliver safe buildings in support of the government’s housing targets."


Featured News

Specification news
TRILUX Opens London Light Studio to Strengthen Customer...

Light. Space. Dialogue.TRILUX has opened a new Light Studio in Charterhouse Square,...

Read More >>

Specification news
Practical action: Cistermiser and Keraflo welcome...

Richard Braid, Managing Director of water saving experts Cistermiser and Keraflo, has...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

2026 Product Brochure Brochure

2026 Product Brochur...
By ​The Radiator Compan...

Download Now >>

System for Laying Floor and Wall Coverings Brochure

System for Laying Fl...
By FassaFloor

Download Now >>

Training for Excellence Brochure

Training for Excelle...
By Aico

Download Now >>

The Connected Home Solution Brochure

The Connected Home S...
By Aico

Download Now >>

Safety First, Aico First Brochure

Safety First, Aico F...
By Aico

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Glass Partition Walls
Glass Partition Walls

Partition wall systems made of glass allow transparent room partition. They open, divide and...

Read More >>

FASSAFILL MEDIUM
FASSAFILL MEDIUM

Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...

Read More >>

FASSA AQUAZIP FAST
FASSA AQUAZIP FAST

Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

DAB EsyBox Pop | Compact booster pump for perfect home water pressure
DAB EsyBox Pop | Compact booster pump for perfect home water pressure

Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...

Watch Now >>

Marsh Industries - Phos-Lite
Marsh Industries - Phos-Lite

Marsh Industries - Phos-Lite

Watch Now >>

Marsh Industries - Nutra-Lite
Marsh Industries - Nutra-Lite

Marsh Industries - Nutra-Lite

Watch Now >>