Latest News Fri, Mar 14, 2025 7:42 AM
The North Lincolnshire Green Energy Park application has today been granted development consent by the Secretary of State for Energy Security and Net Zero.
The scheme consists of an Energy Recovery Facility (ERF) converting up to 650,000 tonnes per annum of Refuse Derived Fuel (RDF) to generate a maximum of 95 Mega Watts of electrical output (MWe) and/or 380 Mega Watts of thermal output (MWt) to provide power, heat and steam on the site of the operating Flixborough Wharf on the River Trent.

The application was submitted to the Planning Inspectorate for consideration by North Lincolnshire Green Energy Park Limited on 31 May 2022 and accepted for Examination on 27 June 2022.
Following an Examination during which the public, Statutory Consultees and Interested Parties were given the opportunity to give evidence to the Examining Authority, recommendations were made to the Secretary of State on 15 August 2023.
This is the 90th energy application out of 150 applications examined to date and was again completed by the Planning Inspectorate within the statutory timescale laid down in the Planning Act 2008.
Local communities continue to be given the opportunity of being involved in the examination of projects that may affect them. Local people, the local authority and other Interested Parties were able to participate in this six-month Examination.
The Examining Authority listened and gave full consideration to all local views and the evidence gathered during the Examination before making its recommendation to the Secretary of State.
Featured News
With their ability to expand and contract to guarantee seals that alternative wet...
Light. Space. Dialogue.TRILUX has opened a new Light Studio in Charterhouse Square,...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
2026 Product Brochur...
By The Radiator Compan...
System for Laying Fl...
By FassaFloor
Training for Excelle...
By Aico
The Connected Home S...
By Aico
Safety First, Aico F...
By Aico
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Partition wall systems made of glass allow transparent room partition. They open, divide and...
Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...
Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...
CONSTRUCTION VIDEOS - LATEST VIDEOS
Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...