Latest News Wed, Jul 12, 2023 6:38 AM
More than a thousand clean energy projects with planning permission are waiting to be built, the Local Government Association warns, with net zero ambitions at risk of being scuppered if grid connection challenges are not fixed.
Hundreds of solar and wind farms are ready to be built, but communities are waiting years, in some cases decades for their clean energy due to delays in projects to the national grid.
For example, plans have been submitted for a solar farm in Coventry but the earliest it can be connected to the grid is 2028. In Dorset, it has become almost impossible to secure grid connections with some projects being told they cannot be connected until 2036.
The LGA is calling on the Government to step up the pace in connecting energy schemes to the grid, and resource councils to develop local energy plans to share investments and develop local grids.
There has been a sharp increase in clean power schemes granted permission by councils in recent years, with the number doubling almost every year since 2018. These projects include schemes to generate energy from solar, wind, water, biomass, waste, sewage, and hydrogen, which have the total capacity to generate 9,000 megawatts at any one time.
The LGA said communities have said yes to over 1,300 renewable energy schemes that are waiting to be built. However, just 150 of these projects are currently under construction.
The solar schemes awaiting construction would alone generate around 15,000 megawatts a day, enough to power 1.9 million homes.
Challenges in connecting new energy power projects to the national grid are often cited as being the key challenge to getting projects off the ground.
Councils are at the forefront of a local energy revolution but need resourcing into local energy plans to help inform grid investments that connect renewable power into homes and cars in communities.
Cllr Linda Taylor, environment spokesperson for the LGA, said: “Our transition to a secure and sustainable future relies on continued growth in renewable energy.
“It’s fantastic to see a rapid rise in planning permissions for green energy projects. However, the numbers awaiting construction is concerning, with many pointing to delays in securing the grid infrastructure that connects solar panels to kettles.
“It’s a big challenge and there is a huge effort underway. Councils want to play their full role but need the resources and powers for local energy plans to shape the grid investments so essential to a secure and sustainable future.”
Featured News
The new President of BEAMA is Erika Wilson, Managing Director of Wilson Power...
Enhance Your Expertise in Resin Flooring: CPD Seminar with Arturo FlooringArturo...
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...
The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...
Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...
CONSTRUCTION VIDEOS - LATEST VIDEOS
“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...
Portakabin | Installation at the iconic Admiralty Arch, London