Government has lost track of its own plan for HS2 Euston, say MPs

Latest News Fri, Jul 7, 2023 6:03 AM

The Department for Transport (DfT) still does not know what it is trying to achieve with the High Speed 2 (HS2) station at Euston, despite spending over eight years planning and designing it.

In March 2023, the DfT announced that it would be pausing new construction work at Euston for the next two years.

In a highly critical report noting multiple different iterations for the project, the Public Accounts Committee (PAC) calls on DfT to use the current pause in construction on the project to finally establish the design and expectations for the station against what it is willing to spend.

The DfT does not yet know the costs and impacts of the pause for the local community, with work still to be done on making the site safe and potentially useable by local residents during the pause. The PAC is also unconvinced that the impact for the DfT’s supply chain, in particular for smaller businesses involved in the works, will be mitigated by their employment elsewhere on the HS2 scheme.

The DfT’s decision to pause followed estimates of a £4.8 billion cost to build the station, compared to an original £2.6 billion budget, which was completely unrealistic. Previous updates to Parliament on cost pressures at Euston did not disclose the risks that construction costs could be significantly higher than unexpected for the station left undisclosed by the DfT. The PAC calls on the Department to provide greater transparency in its six-monthly updates to Parliament.

Questions also remain as to how the Government will manage high levels of inflation on the HS2 programme. The PAC’s inquiry heard the HS2 project is seeing 30% to 40% swings in the cost of raw material. The Treasury has made clear that departments are expected to absorb the higher costs from inflation within existing cash budgets. The DfT and Treasury have not yet reached an understanding on how to deal with this without taking decisions which would risk poor value for money on the project, including further reductions in spending.

Dame Meg Hillier MP, Chair of the Committee, said: “The HS2 Euston project is floundering. This is a multi-billion pound scheme which has already caused major disruption to the local community put on pause. The pause, ostensibly to save money, is not cost free – mothballing and possible compensation for businesses which have lost work will all need to be added to the HS2 tally. The Government must now be clear what it is trying to achieve with this new station, and how it will benefit the public.

“Our report finds that a wildly unrealistic budget for HS2 Euston was set in 2020 in the expectation that it would be revised. The Government must demonstrate that that it is not just repeating the same mistakes of unrealistic costings.

“HS2 Euston has shown us that forging ahead over-optimistically in an unclear direction is clearly not the right approach.”

Featured News

Specification news
Designing Wet Rooms in Modern Construction: Key...

Wet rooms have become a standout feature of new-build residential and mixed-use...

Read More >>

Specification news
Grant Westfield to demonstrate practical and stylish...

Grant Westfield, the company behind leading wall panel brands Multipanel and...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

2026 Product Brochure Brochure

2026 Product Brochur...
By ​The Radiator Compan...

Download Now >>

System for Laying Floor and Wall Coverings Brochure

System for Laying Fl...
By FassaFloor

Download Now >>

Training for Excellence Brochure

Training for Excelle...
By Aico

Download Now >>

The Connected Home Solution Brochure

The Connected Home S...
By Aico

Download Now >>

Safety First, Aico First Brochure

Safety First, Aico F...
By Aico

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Glass Partition Walls
Glass Partition Walls

Partition wall systems made of glass allow transparent room partition. They open, divide and...

Read More >>

FASSAFILL MEDIUM
FASSAFILL MEDIUM

Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...

Read More >>

FASSA AQUAZIP FAST
FASSA AQUAZIP FAST

Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

DAB EsyBox Pop | Compact booster pump for perfect home water pressure
DAB EsyBox Pop | Compact booster pump for perfect home water pressure

Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...

Watch Now >>

Marsh Industries - Phos-Lite
Marsh Industries - Phos-Lite

Marsh Industries - Phos-Lite

Watch Now >>

Marsh Industries - Nutra-Lite
Marsh Industries - Nutra-Lite

Marsh Industries - Nutra-Lite

Watch Now >>