Green power goals jeopardised by lack of overarching Government plan

Latest News Wed, Jun 21, 2023 6:55 AM

The UK Government has a challenging ambition to decarbonise the power sector by 2035 – but no overarching delivery plan exists to do so.

A Public Accounts Committee (PAC) report finds that while the Government has many separate ongoing power decarbonisation plans, its ambitions are jeopardised by the lack of an integrated and coherent delivery plan. This should be pulled together by autumn 2023 at the latest.

The Government’s delivery plan must also set out when and how the costs of decarbonising the power sector will be likely to have an impact on energy bill payers and taxpayers.

The costs to build, maintain and operate the power system are typically passed onto consumer bills, but the Government has not yet assessed what the costs of the clean energy transition ultimately mean for the general public. The Government’s plans to improve energy efficiency and change consumer behaviour, both key to meeting net zero, are not clear.

The PAC is sceptical that the Government’s plans for expanding nuclear, solar and wind power are credible and calls for annual progress updates to Parliament. The UK’s current operating capacity is a quarter of the goals set for nuclear, solar and offshore wind power, with expansion plans relying in part on technology still at an early stage.

The inquiry heard that the Government’s focus on providing energy bill support to manage high gas prices (including due to Russia’s invasion of Ukraine) distracted it from longer-term activities on decarbonisation.

The Government estimates that up to £400 billion of public and private investment in new generating capacity will be needed by 2037, but the PAC is unconvinced that the private sector has been given enough clarity to confidently invest. Stop-start approaches have been highlighted before by the PAC, in reports on environmental tax measures, low emission cars and the Green Homes Grant Voucher Scheme. Investor confidence can be eroded by changes in direction on policy, and the PAC calls for the Government’s delivery plan to set out how it will provide greater clarity to the private sector to encourage the required investment.

Dame Meg Hillier MP, Chair of the Committee, said: “What is the plan? It has now long been understood and accepted that greening our economy is an existential priority, with the Government setting itself the target of securing an entirely low-carbon power supply by 2035. But without a coherent delivery plan to get there, the Government will find it harder to know what decisions it must take, and when, to ensure that it can realistically reach its ambitions.

“There are just twelve years left for the Government to meet its low carbon energy target, and much still to do if this is to be achieved – and at a cost the taxpayers and bill payers can bear while ensuring the lights stay on.

"There is an information vacuum in key areas – energy efficiency, investment, the cost of the transition to the public – that must be addressed. We need an overarching plan charting the way, to provide much-needed confidence to the businesses and consumers who are needed to deliver it. When it comes to tackling the climate crisis, we can see around us, we are already living on borrowed time.”

Featured News

Specification news
Shifting world order makes supply chain security...

The Government has outlined its Critical Minerals Strategy covering the materials...

Read More >>

Specification news
Government warned to stop the self-inflicted damage to...

New data has revealed that net additions to England’s housing supply have declined...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

ACO Blue Roof Guide – Vol 2 Brochure

ACO Blue Roof Guide...
By ACO Building Drainag...

Download Now >>

Stannah Commercial Brochure Brochure

Stannah Commercial B...
By Stannah Group

Download Now >>

Stannah Midilift CLS Brochure

Stannah Midilift CLS
By Stannah Group

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Supreme Heavy-Duty Loft Ladder
Supreme Heavy-Duty Loft Ladder

The Supreme heavy-duty loft ladder is supplied as a ready to fit unit. It is manufactured from high...

Read More >>

Designo Loft Ladder
Designo Loft Ladder

Insulated and Airtight wooden loft ladder……sets the standard for long-lasting quality and...

Read More >>

Elite Loft Ladder
Elite Loft Ladder

The Elite heavy-duty loft ladder...The Elite heavy duty concertina loft ladder is supplied without a...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Proctor Air® Product Explainer
Proctor Air® Product Explainer

Proctor Air® is an air and vapour permeable, highly water resistant roofing underlay. Its...

Watch Now >>

Discover the Power of Blue Roofs in Urban Flood Management
Discover the Power of Blue Roofs in Urban Flood Management

In this video, we explore how blue roofs are transforming urban landscapes by helping to mitigate...

Watch Now >>

RMD Profiles - UK Experts in Metal Decking, Design Installation
RMD Profiles - UK Experts in Metal Decking, Design Installation

At RMD Profiles, we’re more than just metal decking. From supply-only solutions to full design and...

Watch Now >>