Westbury Hotel lifted to build basement

Latest News Wed, Apr 12, 2023 6:26 AM

The Special Projects team at Sir Robert McAlpine have taken on the challenge to create two added layers of basement at The Westbury as part of a project designed to breathe new life into this landmark luxury hotel.

They have been able to draw on the inhouse expertise of colleagues across the business, including members of the McAlpine Lifting Solutions, Geospatial Engineering, and McAlpine Design Group teams, as they look to tackle the various complex engineering challenges presented by the job.

The scheme has involved removing the rear of the concrete frame building and digging down two further levels, extending both out to the site boundary and underneath the existing structure. Once these works are complete, installation of a full height steel frame extension will be significantly increasing the hotel’s square footage.

But how to hold the building up while we excavate underneath it, remove the old foundations, dig the basement out and install new foundations for the extended structure to sit on?

Step forward McAlpine Design Group, who worked with the project team to develop a solution which involved creating a temporary set of foundations for each existing concrete column.

Under the design, four new piles were drilled 26 metres into the ground through each of the existing foundations and a new steel frame constructed on top to temporarily take the weight of the building off each column.

The weight of the seven storey building was then carefully transferred onto these new temporary foundations using hydraulic jacks.

With the building supported, the team could then start to remove the old foundations and excavate the two new basement floors.

Once the basement is complete, new, permanent steel columns will be installed to extend the existing columns down to the pile caps at the lowest point of the basement.

The weight of the building will then be transferred over to its new foundations and the temporary works removed.

Featured News

Specification news
Hybrid tapes: future proof buildings and property

With their ability to expand and contract to guarantee seals that alternative wet...

Read More >>

Specification news
TRILUX Opens London Light Studio to Strengthen Customer...

Light. Space. Dialogue.TRILUX has opened a new Light Studio in Charterhouse Square,...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

2026 Product Brochure Brochure

2026 Product Brochur...
By ​The Radiator Compan...

Download Now >>

System for Laying Floor and Wall Coverings Brochure

System for Laying Fl...
By FassaFloor

Download Now >>

Training for Excellence Brochure

Training for Excelle...
By Aico

Download Now >>

The Connected Home Solution Brochure

The Connected Home S...
By Aico

Download Now >>

Safety First, Aico First Brochure

Safety First, Aico F...
By Aico

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Glass Partition Walls
Glass Partition Walls

Partition wall systems made of glass allow transparent room partition. They open, divide and...

Read More >>

FASSAFILL MEDIUM
FASSAFILL MEDIUM

Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...

Read More >>

FASSA AQUAZIP FAST
FASSA AQUAZIP FAST

Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

DAB EsyBox Pop | Compact booster pump for perfect home water pressure
DAB EsyBox Pop | Compact booster pump for perfect home water pressure

Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...

Watch Now >>

Marsh Industries - Phos-Lite
Marsh Industries - Phos-Lite

Marsh Industries - Phos-Lite

Watch Now >>

Marsh Industries - Nutra-Lite
Marsh Industries - Nutra-Lite

Marsh Industries - Nutra-Lite

Watch Now >>