HS2 reveals progress of first ‘green tunnels’

Latest News Mon, Jan 10, 2022 7:21 AM

HS2 has revealed the first images of the longest of three innovative ‘green tunnels’ that will be built across Buckinghamshire and Northamptonshire to help blend the new high-speed rail line into the landscape and reduce disruption for residents.

The one-and-a half-mile long Greatworth tunnel will be built in a factory in Derbyshire before being shipped to site and assembled over the railway line as it passes the village. It will then be covered with earth and landscaped to fit into the surrounding countryside.

Applying lessons from the construction of the latest French high speed lines, an ‘off site’ modular approach was developed by HS2’s main works contractor, EKFB - a team made up of Eiffage, Kier, Ferrovial Construction and BAM Nuttall.

Designed as an ‘m’ shaped double arch, the tunnel will have two separate halves for southbound and northbound trains. Instead of the whole tunnel being cast on site, five different concrete precast segments will be slotted together to achieve the double arch - one central pier, two side walls and two roof slabs. All 5,400 segments installed at Greatworth will be steel reinforced, with the largest weighing up to 43 tonnes.

Concrete and steel are some of the biggest sources of carbon emissions within the construction industry and by reducing the amount of both materials needed for the tunnel, this lighter-weight modular approach is expected to more than halve the amount of carbon embedded in the structure. It also requires less people and equipment on site, improving safety and reducing disruption for residents.

HS2 Ltd’s Project Client Rohan Perin, said: The Greatworth green tunnel is a great example of what we’re doing to blend the new railway into the landscape and protect communities living close to the line. By adopting an ‘off site’ approach to manufacturing, we’re also cutting embedded carbon from the design, improving efficiency, safety and making the whole construction process less disruptive for the community.”

EKFB Delivery Director Andy Swift, said: “The green tunnel design is a combination of innovation, international engineering expertise and thoughtful landscaping for its local communities to enjoy. Once the tunnels have been built, the original earth removed from the cutting to make way for the tunnel, will be repositioned, creating a green space which will blend into the surrounding landscape.”

Similar structures will also be built near Wendover in Buckinghamshire and Chipping Warden in Northamptonshire, stretching for a combined total of four miles. The tunnels will all have specially designed ‘porous portals’ at either end to reduce the noise of trains entering and exiting the tunnel and small portal buildings to house safety and electrical equipment.

Thousands of tonnes of rock and earth will be excavated during the initial stages of construction. These will be carefully separated and stockpiled on site for reuse later in the process, helping to keep trucks off local roads.

Tailored landscaping design plans will be developed for each tunnel, with thousands of native trees and shrubs typical to the local area, such as, Silver Birch, Oak, Beech and Willow planted to create new woodland areas around the portals and recreate the hedgerows and field boundaries on top of the tunnel.

All 13,290 segments for the three tunnels are being made by Derbyshire-based Stanton Precast Ltd, in a deal which has created almost 100 jobs at their Ilkeston factory. Stanton currently employs around 180 people at their factory and this deal has enabled the firm to increase their workforce by around 50%. New production sheds, casting and storage areas are also being built at the factory to accommodate the new work.

Featured News

Specification news
RICS launches consultation on updated Home Survey...

The Royal Institution of Chartered Surveyors (RICS) announces the launch of a public...

Read More >>

Specification news
Scotland’s first Passivhaus school with swimming pool...

A new chapter in sustainable education has begun with the completion of Currie...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Vertical radiators complete range Brochure

Vertical radiators c...
By Myson

Download Now >>

Myson Radiant Heating Premium underfloor heating systems Brochure

Myson Radiant Heatin...
By Myson

Download Now >>

Which heat emitter is the right one? Brochure

Which heat emitter i...
By Myson

Download Now >>

Sustainable heating solutions for renovation Brochure

Sustainable heating...
By Myson

Download Now >>

Rearo Tradeline Brochure

Rearo Tradeline
By Rearo

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

DUOFLEX
DUOFLEX

DUOFLEX is a high quality elastomeric bitumen, hot bonded to the substrate incorporating the fleece...

Read More >>

TECSOUND
TECSOUND

TECSOUND is a polymer based, bitumen-free, high-density synthetic membrane. The combination of its...

Read More >>

ISOLAIR MULTI
ISOLAIR MULTI

ISOLAIR MULTI is a natural and ecological vapour-permeable, windproof and water-repellent thermal...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Our SUSTAINABILITY Roadmap
Our SUSTAINABILITY Roadmap

Myson has a clear sustainability strategy in line with the UN Sustainable Development Goals (SDGs)...

Watch Now >>

Sustainable Energy Efficient Solutions
Sustainable Energy Efficient Solutions

From radiators and underfloor heating to ceiling convectors and towel warmers, Myson is the UK’s...

Watch Now >>

UNISENZA PLUS Smart Controls_The complete system solution
UNISENZA PLUS Smart Controls_The complete system solution

With Unisenza Plus Smart Controls you can easily monitor and control all linked heating products via...

Watch Now >>