Energy and transport crisis pushes cost of steelwork up

Latest News Wed, Nov 10, 2021 7:01 AM

New research reveals yet further hikes in materials costs, with the added energy and transportation crisis creating a perfect storm of limited raw materials supply, products and labour.

With the cost of steelwork up by a further 17% in the last three months alone and 38% over the last 12 months, contractors warn that the volatility of the market means that the supply chain can no longer forecast and fix building costs.

The research was carried out by the Southern Construction Framework (SCF), a leading construction procurement framework delivered by the public sector for the public sector in the South of England. Its latest quarterly report is based on data from July to September 2021 in partnership with its Main Contractors (BAM; GallifordTry; Isg; KIER; mace; midas; Morgan Sindall; Sir Robert McAlpine; Wates; Willmott Dixon).

In this quarter’s report, SCF’s Main Contractors have described the market volatility and the rate of price increases as ‘truly unprecedented’, with some referring to subcontractors fixing prices for just 24 hours, making planning across the industry impossible.

For Q3 alone, SCF’s Main Contractor’s supply chains have reported an average building cost increase of 12% across all trades - due to a combination of inflation rates across numerous products and materials. The price of some raw materials, specifically metals, has continued to impact on the building costs of many trades and products.

Trades that have seen the greatest increase in Q3 when compared to the previous quarter include Steelwork (17%); Carpentry & Joinery (16%); Curtain Walling & Dry Lining (14%); Windows (13%).

Over the last 12 months the greatest annual building cost increases have been found in Steelwork (38%); Dry Lining (18%); M&E (16%); Carpentry & Joinery (15%).

Kingsley Clarke, SCF Operations Lead said: “The cost of steelwork has shot up in the last year and in the next quarterly report due out in December, this is likely to be up again, given British Steel’s new surcharge in response to the mounting price of gas and transportation. Whilst it is temporary, a £30 per tonne price increase on already inflated costs is the last thing that contractors need in addition to all the additional knock-on challenges of materials and labour shortages and rising salaries.”

This quarter’s report also reveals the impact on material distribution of the lack of HGV drivers from a reduction in European workforce, compounded by the misplacement of global shipping containers and the cost of petrol rising sharply, recently hitting an all-time record.

The knock-on effect is that trades have experienced an even greater increase in material and labour lead time during Q3 when compared to the previous year. The trades most impacted are Steelwork (additional 7 weeks); Brickwork, Dry Lining and Tower Crane (additional 4 weeks); Curtain Walling, Groundworks & Windows (additional 3 weeks).

Adam Sanford, SCF Operations Lead added: “There is no easy way to solve the problems we face, but early collaboration is one way to help mitigate some of the crippling issues facing the industry. Early engagement with the Main Contractor means you can work together to ensure that design solutions incorporate current market pressures before detailed design. For SCF projects, our Main Contractors are committed to sharing early advice, even prior to appointment.

“We also recommend a transparent approach to project budgets, risk allocation and pricing to ensure an environment in which market risks can be effectively managed and mitigated, reducing uncertainty in procurement, and increasing certainty on costs.”

To get a copy of the report, please go to Market Intelligence - SCF (scfconstruct.org.uk)

Featured News

Specification news
Renson at the Old War Office: Historic elegance, modern...

The historic Old War Office (OWO), a Grade II* listed neo-Baroque landmark in central...

Read More >>

Specification news
RICS launches consultation on updated Home Survey...

The Royal Institution of Chartered Surveyors (RICS) announces the launch of a public...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Vertical radiators complete range Brochure

Vertical radiators c...
By Myson

Download Now >>

Myson Radiant Heating Premium underfloor heating systems Brochure

Myson Radiant Heatin...
By Myson

Download Now >>

Which heat emitter is the right one? Brochure

Which heat emitter i...
By Myson

Download Now >>

Sustainable heating solutions for renovation Brochure

Sustainable heating...
By Myson

Download Now >>

Rearo Tradeline Brochure

Rearo Tradeline
By Rearo

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

DUOFLEX
DUOFLEX

DUOFLEX is a high quality elastomeric bitumen, hot bonded to the substrate incorporating the fleece...

Read More >>

TECSOUND
TECSOUND

TECSOUND is a polymer based, bitumen-free, high-density synthetic membrane. The combination of its...

Read More >>

ISOLAIR MULTI
ISOLAIR MULTI

ISOLAIR MULTI is a natural and ecological vapour-permeable, windproof and water-repellent thermal...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Our SUSTAINABILITY Roadmap
Our SUSTAINABILITY Roadmap

Myson has a clear sustainability strategy in line with the UN Sustainable Development Goals (SDGs)...

Watch Now >>

Sustainable Energy Efficient Solutions
Sustainable Energy Efficient Solutions

From radiators and underfloor heating to ceiling convectors and towel warmers, Myson is the UK’s...

Watch Now >>

UNISENZA PLUS Smart Controls_The complete system solution
UNISENZA PLUS Smart Controls_The complete system solution

With Unisenza Plus Smart Controls you can easily monitor and control all linked heating products via...

Watch Now >>