Latest News Wed, Aug 25, 2021 5:34 AM
The overall construction materials and product supply situation has not changed substantially, there has been a temporary easing in recent weeks.
But industry leaders maintain this is most likely due to a combination of the holiday period and some domestic customers delaying or cancelling projects due to higher costs or cost uncertainty.
Timber, cement, roofing products, bricks, blocks, insulation, steel and cable management systems remain the products in shortest supply, while global shortages of semi-conductors are a cause for concern in the lighting and appliance sectors. Although product and material price inflation has slowed, indications are that it will be 2022 before prices stabilise, with some manufacturers still to implement double digit price increases to recover current and future cost inflation.

Haulage, however, and the lack of availability of drivers, are now the major concerns affecting distribution with some suppliers asking builders merchants to collect their orders as they cannot get enough drivers to complete deliveries. Regional distribution is a particular issue, with some finding challenges arranging deliveries to Scotland and the South West of England.
In their latest statement, John Newcomb, CEO of the Builders Merchants Federation and Peter Caplehorn, CEO of the Construction Products Association, co-chairs of the Construction Leadership Council’s Product Availability working group, said the logistics problem is not limited to thisr sector, and with similar haulage issues affecting a wider distribution network there is no short-term fix.
“The Department for Transport is engaging with the freight sector and hauliers to look at both interim and longer-term solutions, which require collaboration between government and the sector,” they said.
“Container shipping continues to affect imports. Key ports in China are suffering reduced capacity due to Covid, but the backlog extends beyond China throughout distribution centres worldwide. This is forecast to continue through the peak Christmas season into early 2022. With capacity at a premium, container prices remain high; however, these rates are not sustainable in the long term and when demand signals change, we are likely to see prices reduce.
“Looking forward, the group discussed the requirement for aggregates and other key products when HS2 demand is at its peak in 2022/23. Projected volumes are being shared with industry trade bodies, key suppliers and the CLC Product Availability Group to help provide greater clarity and confidence about the industry’s ability to deliver HS2 as well as all other projects. This is a particular concern for smaller builders, who have struggled to compete for supply during the current period of extraordinary demand.”
Featured News
The NHBC Foundation has published a new report – the Water Compendium. This...
Polyflor, the UK's commercial and residential vinyl flooring specialist, is delighted...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
ACO Blue Roof Guide...
By ACO Building Drainag...
Stannah Commercial B...
By Stannah Group
Levelmaster
By Stannah Group
Trolleylift
By Stannah Group
Stannah Midilift CLS
By Stannah Group
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
The Supreme heavy-duty loft ladder is supplied as a ready to fit unit. It is manufactured from high...
Insulated and Airtight wooden loft ladder……sets the standard for long-lasting quality and...
The Elite heavy-duty loft ladder...The Elite heavy duty concertina loft ladder is supplied without a...
CONSTRUCTION VIDEOS - LATEST VIDEOS
Proctor Air® is an air and vapour permeable, highly water resistant roofing underlay. Its...
In this video, we explore how blue roofs are transforming urban landscapes by helping to mitigate...
At RMD Profiles, we’re more than just metal decking. From supply-only solutions to full design and...