Construction activity continues to be strong across the UK, with government statistics and industry surveys indicating this is primarily led by the new housing, housing RMI and infrastructure sectors.
Evidence suggests a positive pipeline of work ahead, including a high level of contracts awarded during the first quarter.
With full order books, the current level of active demand across the entire construction industry will continue to put increasing pressure on the product supply chain.
In general, products are available but lead times have lengthened. Current demand is such that it is proving difficult for manufacturers and suppliers to build up stock levels.
In a joint statement, John Newcomb, CEO of the Builders Merchants Federation and Peter Caplehorn, CEO of the Construction Products Association, co-chairs of the Construction Leadership Council’s Product Availability working group, said the worst affected product areas continue to be timber, roof tiles and roofing membranes.

“There is unlikely to be any improvement in timber supplies this year with little or no timber currently coming into the UK that is not already pre-sold and global demand outstripping supply,” they continued. “However, the supply of roofing products is expected to improve in the second half.
“Raw material shortages, stemming from global demand and other external factors such as factory closures outside the UK, continue to constrain production of PE and PP plastics, PIR insulation, paints, adhesives and other coatings, and also packaging for other product groups.
“Global demand also continues to impact prices and delivery times on structural steel, internal steel products and galvanised steel. Evidence suggests that some steel products may suffer continued shortages into the second half of the year.
“Pent up demand for landscaping products over the spring and summer may place an additional burden on supplies, but demand will continue to be met with longer lead times where needed.
“Accurate forecasting can help alleviate availability issues. The CPA’s latest forecast was published this week and the BMF will publish their latest forecasts in May.
“The CLC’s key advice is to plan in advance, work closely with your supply chain and communicate your requirements early with suppliers, distributors and builders merchants. Collaborative, ongoing communication throughout the whole supply chain is essential.”
The Product Availability Group is also exploring further solutions to alleviate other bottle necks in the supply chain such as logistics and transport, including the ability to accept deliveries outside of normal opening hours.
Featured News
Light. Space. Dialogue.TRILUX has opened a new Light Studio in Charterhouse Square,...
Richard Braid, Managing Director of water saving experts Cistermiser and Keraflo, has...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
2026 Product Brochur...
By The Radiator Compan...
System for Laying Fl...
By FassaFloor
Training for Excelle...
By Aico
The Connected Home S...
By Aico
Safety First, Aico F...
By Aico
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Partition wall systems made of glass allow transparent room partition. They open, divide and...
Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...
Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...
CONSTRUCTION VIDEOS - LATEST VIDEOS
Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...