Latest News Wed, Apr 7, 2021 11:29 AM
The Construction Leadership Council has released an official statement on the continuing problems facing the industry as regards product and material availability.
Demand for construction products remains high both in the UK and globally and is set to continue throughout 2021 in every sector.
John Newcomb, CEO Builders Merchants Federation and Peter Caplehorn, CEO Construction Products Association, co-chairs of CLC Product Availability work group, said unfortunately, this means the availability issues the industry is currently experiencing are likely to worsen before they improve.
“While supplies of plaster and plasterboard are much improved on last year, almost every other product group is experiencing longer lead times and, as a consequence, higher prices,” the statement continued.

“Plastics (PE and PP), cement and aggregates have joined existing lists of products in short supply, including timber, steel, roof tiles, bricks and imported products such as screws, fixing, plumbing items, sanitaryware, shower enclosures, electrical products and appliances.
“Prior to the temporary blockage of the Suez Canal, we were seeing a slight lowering of both container costs and delivery times of these imported goods. We anticipate that this will continue once the effect of the temporary closure works through.
“Imports of timber will be an issue for the foreseeable future. Not enough timber is being produced to meet world demand. Added to this, other countries are prepared to pay more to secure their supply, pushing the UK lower down the pecking order.
“Steel is also experiencing strong global demand. While supply and demand are likely rebalance within the next few months, global dynamics will continue to drive prices up.
“Raw material shortages constraining polymer supplies are causing production problems for plastics (lower ground drainage etc). Coatings manufacturers are also experiencing raw material shortages beyond their control, at a time when demand is particularly high. These issues will continue for at least 2-3 months.
“All users should plan for increased demand and longer delays, keep open lines of communication with their suppliers and order early for future projects.”
The CLC’s product availability group will continue to monitor the situation. The CPA and the BMF – who jointly chair the group – produce quarterly forecasts on market activity which is helping manufacturers to plan output.
Featured News
With their ability to expand and contract to guarantee seals that alternative wet...
Light. Space. Dialogue.TRILUX has opened a new Light Studio in Charterhouse Square,...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
2026 Product Brochur...
By The Radiator Compan...
System for Laying Fl...
By FassaFloor
Training for Excelle...
By Aico
The Connected Home S...
By Aico
Safety First, Aico F...
By Aico
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Partition wall systems made of glass allow transparent room partition. They open, divide and...
Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...
Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...
CONSTRUCTION VIDEOS - LATEST VIDEOS
Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...