Latest News Wed, Apr 7, 2021 11:29 AM
The Construction Leadership Council has released an official statement on the continuing problems facing the industry as regards product and material availability.
Demand for construction products remains high both in the UK and globally and is set to continue throughout 2021 in every sector.
John Newcomb, CEO Builders Merchants Federation and Peter Caplehorn, CEO Construction Products Association, co-chairs of CLC Product Availability work group, said unfortunately, this means the availability issues the industry is currently experiencing are likely to worsen before they improve.
“While supplies of plaster and plasterboard are much improved on last year, almost every other product group is experiencing longer lead times and, as a consequence, higher prices,” the statement continued.

“Plastics (PE and PP), cement and aggregates have joined existing lists of products in short supply, including timber, steel, roof tiles, bricks and imported products such as screws, fixing, plumbing items, sanitaryware, shower enclosures, electrical products and appliances.
“Prior to the temporary blockage of the Suez Canal, we were seeing a slight lowering of both container costs and delivery times of these imported goods. We anticipate that this will continue once the effect of the temporary closure works through.
“Imports of timber will be an issue for the foreseeable future. Not enough timber is being produced to meet world demand. Added to this, other countries are prepared to pay more to secure their supply, pushing the UK lower down the pecking order.
“Steel is also experiencing strong global demand. While supply and demand are likely rebalance within the next few months, global dynamics will continue to drive prices up.
“Raw material shortages constraining polymer supplies are causing production problems for plastics (lower ground drainage etc). Coatings manufacturers are also experiencing raw material shortages beyond their control, at a time when demand is particularly high. These issues will continue for at least 2-3 months.
“All users should plan for increased demand and longer delays, keep open lines of communication with their suppliers and order early for future projects.”
The CLC’s product availability group will continue to monitor the situation. The CPA and the BMF – who jointly chair the group – produce quarterly forecasts on market activity which is helping manufacturers to plan output.
Featured News
In the fast-paced world of construction, time is often the most valuable resource....
The Royal Institute of British Architects (RIBA) has published its annual Business...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
ACO Blue Roof Guide...
By ACO Building Drainag...
Stannah Commercial B...
By Stannah Group
Levelmaster
By Stannah Group
Trolleylift
By Stannah Group
Stannah Midilift CLS
By Stannah Group
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
The Supreme heavy-duty loft ladder is supplied as a ready to fit unit. It is manufactured from high...
Insulated and Airtight wooden loft ladder……sets the standard for long-lasting quality and...
The Elite heavy-duty loft ladder...The Elite heavy duty concertina loft ladder is supplied without a...
CONSTRUCTION VIDEOS - LATEST VIDEOS
Proctor Air® is an air and vapour permeable, highly water resistant roofing underlay. Its...
In this video, we explore how blue roofs are transforming urban landscapes by helping to mitigate...
At RMD Profiles, we’re more than just metal decking. From supply-only solutions to full design and...