Target missed to make thousands of Grenfell-style cladding homes safe

Latest News Wed, Sep 16, 2020 9:03 AM

Three years after the Grenfell Tower disaster in which 72 people lost their lives, only a third (155 out of 455) of high-rise buildings with Grenfell-style flammable cladding due to be fixed by now have had their cladding replaced with a safe alternative.

In a new report, the Public Accounts Committee says it is “imperative” that the new deadline, for works on the remaining high-rise blocks to be completed by the end of 2021, be met. The Government has no convincing plan for how it will meet that new deadline though, and even if it does there are a host of other serious shortcomings exposed by the Grenfell disaster that also need to be addressed.

The Ministry for Housing, Communities and Local Government accepts that the British system of building safety regulation has been “not fit for purpose” for many years - and these failings have left a legacy of problems for the Department to address which extend far beyond the immediate need to remove dangerous cladding.

A lack of skills, capacity, and access to insurance is hampering efforts to improve or simply assure the structural safety of apartment blocks. This knocks on to any ability to restore the confidence of buyers and mortgage lenders in sales of flats across the country. Leaseholders are in limbo and facing huge bills because of a system-wide failure.

In March 2020 the Department announced that a further £1 billion would be made available to fund the replacement of other forms of dangerous cladding on high-rise buildings – but even by its own estimates, this will meet only around a third of the total costs.

Otherwise, the Government has no plans to support residents or social landlords to meet the costs of replacing dangerous cladding in buildings below 18 metres, of providing ‘waking watches’, or of fixing other serious defects brought to light by post-Grenfell inspections.

Although the Department also recognises that care homes would be at additional risk due to the difficulties in evacuating residents in the event of a fire, it has no knowledge of whether any of the 40,000 care homes, sheltered housing and hospitals below 18 metres in height are clad with unsafe material.

Meg Hillier MP, Chair of the Public Accounts Committee, said: “Thousands of people have been condemned to lives of stress and fear in unsaleable homes with life-changing bills: for the works and for the fire-watch that is necessary to allow them to sleep at night until it is done.

“The government has repeatedly made what turn out to be pie-in-the-sky promises – and then failed to plan, resource, or deliver. The deadly legacy of a shoddy buildings regulation system has been devastating for the victims and survivors of Grenfell but is leaving a long tail of misery and uncertainty for those whose lives are in limbo.

“The Government must step up and show that it will put a stop to the bickering over who is responsible, who’s going to pay for the remediation – and just put this right.”

Featured News

Specification news
A. Proctor Group Collaborates with Park Home...

The introduction of the Building Safety Act 2022 was focused around higher-risk...

Read More >>

Specification news
A. Proctor Group products achieve CCPI assessment

Proctor Group has successfully undertaken assessment of the product information for...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

PVC-U System Fully Reversible Windows by Epwin Window Systems Brochure

PVC-U System Fully R...
By Epwin window systems...

Download Now >>

Spectus Bevelled Windows and Doors Brochure

Spectus Bevelled Win...
By Epwin window systems...

Download Now >>

Vertical Sliding Sash Window Brochure

Vertical Sliding Sas...
By Epwin window systems...

Download Now >>

Two-Part Cill System Brochure

Two-Part Cill System
By Epwin window systems...

Download Now >>

 Spectus Ovolo  Windows and Doors Brochure

Spectus Ovolo Wind...
By Epwin window systems...

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

DUOFLEX
DUOFLEX

DUOFLEX is a high quality elastomeric bitumen, hot bonded to the substrate incorporating the fleece...

Read More >>

TECSOUND
TECSOUND

TECSOUND is a polymer based, bitumen-free, high-density synthetic membrane. The combination of its...

Read More >>

ISOLAIR MULTI
ISOLAIR MULTI

ISOLAIR MULTI is a natural and ecological vapour-permeable, windproof and water-repellent thermal...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

A responsible addition: HIMACS shapes are now SCS-Certified for recycled content
A responsible addition: HIMACS shapes are now SCS-Certified for recycled content

HIMACS has long been the solid surface material of choice for architects and designers looking for a...

Watch Now >>

Our SUSTAINABILITY Roadmap
Our SUSTAINABILITY Roadmap

Myson has a clear sustainability strategy in line with the UN Sustainable Development Goals (SDGs)...

Watch Now >>

Sustainable Energy Efficient Solutions
Sustainable Energy Efficient Solutions

From radiators and underfloor heating to ceiling convectors and towel warmers, Myson is the UK’s...

Watch Now >>