Planning approvals to start on site gap widens

Latest News Tue, May 8, 2018 5:07 AM

The time taken to get construction projects from planning approvals to a start on site has widened by nearly 14% over the past five years according to Glenigan’s construction market research.

The housebuilding sector attracts plenty of criticism over the time taken between securing approval and construction starting on site.

However, Glenigan’s industry analysis suggests claims of landbanking are unfounded. Instead, other sectors are taking far longer.

Over the past five years, the median time for a project to go from an approval to a construction start is 23 months. In 2012, this gap was 22 months but by last year the lag had widened to 25 months.

Glenigan economics director Allan Wilen said: “This research shows that while red tape has been loosened to make planning permission easier, other factors are also part of the reason for the gap.

“Concerns over the economy and the time taken to negotiate a Section 106 agreement are also likely factors, as is the Brexit vote, which was taken in 2016.”

That vote appears to have influenced some sectors reliant on private sector funding, such as hotel & leisure work and retail.

In the hotel and leisure sector, the median time taken from an application being approved to construction work starting on site has extended by nearly a quarter from 2012 to 2017, as operators sit on approved projects.

In the private sector, the gap between a planning application gaining approval and retail sector construction projects starting on site widened by three months between 2012 and 2017.

Retailers have begun to rein in spending as consumers shift towards online shopping and away from the High Street.

As a result, some major grocery chains such as J Sainsbury and Tesco sold off land earmarked for housing, which invariably involves re-submission of a new planning application.

Out of nine building sectors monitored by Glenigan, the area with the biggest gap between planning approval and construction work starting on site is the community & amenity sector.

This sector has suffered from years of cuts to spending at the local authorities, which make up the key clients. Last year, the median gap between approval and construction starting on site was 45 months.

A planning consent lapses after three years. This suggests that swathes of projects in the community & amenity sector are unlikely to be built.

The sector with the shortest time lag is education, where the median time between projects gaining consent and construction starting is 19 months.

However, even here that time has lengthened since 2012, when the median time was 16 months.

The building sectors to record a shortening in the gap between approval and construction starting between 2016 and 2017 were offices, private housing and social housing.

That suggests that the latest landbanking enquiry is likely to absolve the housebuilders again.

Featured News

Specification news
Construction project management contributes £33...

A new report by the Association for Project Management (APM), the chartered...

Read More >>

Specification news
Keepmoat joins forces with BCU to explore energy use in...

Top 10 housebuilder, Keepmoat has partnered with Birmingham City University’s...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

FRAMESAFE FR A2 FIRE RATED EXTERNAL WALL BREATHER MEMBRANE  Brochure

FRAMESAFE FR A2 FIRE...
By Glidevale Protect

Download Now >>

A Guide to Aluminium Fencing Brochure

A Guide to Aluminium...
By F.H. Brundle

Download Now >>

Handrailing & Balustrade Systems Brochure

Handrailing & Balust...
By F.H. Brundle

Download Now >>

RLG600 Access Flooring System Brochure

RLG600 Access Floori...
By Kingspan Data & Floo...

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Straightcurve®
Straightcurve®

Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...

Read More >>

RLG600 Access Flooring System
RLG600 Access Flooring System

The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...

Read More >>

RHG600 Simploc
RHG600 Simploc

Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Straightcurve® Product Range Overview - A Demonstration of Installation Ease
Straightcurve® Product Range Overview - A Demonstration of Installation Ease

Straightcurve® Product Range Overview - A Demonstration of Installation Ease

Watch Now >>

Forma aluminium column casings for Winchester College
Forma aluminium column casings for Winchester College

In progressive and dynamic business sectors, such as construction, it’s natural to be forward...

Watch Now >>

Decorative metal bulkheads & column casings for Tesco Extra, Birmingham
Decorative metal bulkheads & column casings for Tesco Extra, Birmingham

Decorative aluminium horizontal bulkheads more than 100 metres long have been supplied and installed...

Watch Now >>