Rå Build meets the need for speed

Latest News Wed, Jun 8, 2016 3:26 PM

H+H’s Rå Build method has been used by design and build contractor Canning Ericsson to speed construction of a three-storey apartment block on a confined site in Brighton.

Canning Ericsson was already familiar with the advantages of H+H’s Rå Build method of large format aircrete blocks, the Thin-Joint System and quick-drying Celfix Mortar having used the modern construction method on several of its previous schemes.

“We decided to use H+H’s Thin-Joint System again because it is quick and easy to use, it goes up fast and gains structural strength quickly; it’s a really great system,” says Michael Alderton, director of Canning Ericsson.

Aircrete’s structural strength was important because the weight of the project’s cast in situ reinforced concrete first and second floor slabs is carried by the High Strength Thin-Joint Blocks that form the inner leaf of the building’s external cavity wall.

Construction speed was important to the contractor. “The biggest benefit of using H+H’s Thin-Joint System is the ability to use large format 630mm x 250mm x 100mm wide Jumbo Bloks, which enables the walls to be constructed a lot quicker” says Mr Alderton.

The blocks are relatively lightweight and easy to cut to shape in comparison to denser blocks. “The footings were in place mid-October 2014 and by the end of December 2014 we had built the block using aircrete with cast in situ floors and fitted the roof.”

In addition to speeding construction the aircrete blocks also help improve the walls’ thermal performance, reduce sound transmission between apartments and improve the airtightness to help the scheme meet the Code for Sustainable Homes Level 3 criteria.

Using the Thin-Joint System also helped Canning Ericsson overcome the limited storage facilities on the compact site because the Celfix mortar is delivered bagged and can be mixed in buckets, which eliminates the need to store sand and other materials on site.

Featured News

Specification news
RIBA Presidential Taskforce meets to tackle unhealthy...

The Royal Institute of British Architects (RIBA) has launched a taskforce of leading...

Read More >>

Specification news
RTPI commissions research into futureproofing the next...

A new research project commissioned by the Royal Town Planning Institute (RTPI) will...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

HPS200 Ultra Case Study Brochure Brochure

HPS200 Ultra Case St...
By Tata Steel

Download Now >>

Confidex Datasheet Brochure

Confidex Datasheet
By Tata Steel

Download Now >>

Prisma UK 2024 Brochure

Prisma UK 2024
By Tata Steel

Download Now >>

HPS200 Ultra UK Brochure

HPS200 Ultra UK
By Tata Steel

Download Now >>

Amtico Bio Support Document  Brochure

Amtico Bio Support D...
By Amtico

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

​The Confidex® Guarantee
​The Confidex® Guarantee

Offers the most comprehensive guarantee for pre-finished steel products in Europe and provides peace...

Read More >>

Colorcoat HPS200 Ultra®
Colorcoat HPS200 Ultra®

Colorcoat HPS200 Ultra®Super durable guaranteed performance.Designed to withstand even the most...

Read More >>

Prisma
Prisma

Colorcoat Prisma®Aesthetics that last, guaranteed.Colorcoat Prisma® demonstrates a step change by...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Mira Vista Heatloop
Mira Vista Heatloop

Mira Showers is delighted to introduce the new Mira Vista HeatloopTM – an innovative and stylish...

Watch Now >>

Why our Canopies Last Longer
Why our Canopies Last Longer

https://www.aandslandscape.co.uk/ Find out why A&S Landscape Canopies last longer than alternatives....

Watch Now >>

Enclosed Dining Canopy - Hampton Gardens School
Enclosed Dining Canopy - Hampton Gardens School

A&S Landscape designed and installed a large enclosed, curved roof canopy for Hampton Gardens School...

Watch Now >>