Quarter of the UK Government construction pipeline disappears

Latest News Wed, Mar 23, 2016 9:16 AM

Quarter of the UK Government construction pipeline disappears

With more than a quarter of its projects disappearing since December 2014, more needs to be done to improve the consistency and accuracy of the UK Government construction pipeline, according to analysis published by KPMG.

The report, UK Government Construction Pipeline - KPMG Analysis, indicates that there is a total decrease of 886 (28%) construction and infrastructure projects since the previous pipeline analysis in December 2014 (from 3,148 to 2,262 in August 2015), relating mainly to the Defence, Justice and Police sectors (860 projects alone relate to these sectors).

KPMG understands that the remarkable decrease in the number of projects is largely due to potential projects being removed from the pipeline to avoid pre-empting decisions in the forthcoming Spending Review. There are also a number of projects that have been completed since the December 2014 iteration.

Most of the decrease in value attribute to projects completing mainly in two sectors:

  • £6.7 billion decrease in Transport projects - relating to spend already incurred on a number of ongoing programmes, including Crossrail.
  • £2.8 billion decrease in Housing and Regeneration projects – relating to the completion of Decent Homes Backlog projects and a number of Affordable Housing projects and programmes also completed.

The analysis went on to reveal that 1,784 projects did not specify a construction start date, further raising questions about the completeness of the data.

The report also found that:

  • Transport and energy continue to dominate the pipeline, mirroring the National Infrastructure Pipeline, with nearly 70% of the pipeline (£82.1 billion) designated to these two sectors alone, despite only contributing 9% of the entire pipeline of projects by volume.
  • Defence, Justice and Police Forces projects account for over 74% of projects (1,672 projects inclusive) by volume, but only 10% (£11.4 billion) of total allocated spend. Spend across these three sectors relates to refurbishment, maintenance programmes and minor improvements/ small works/ new capital programmes.

Richard Threlfall, KPMG’s UK Head of Infrastructure, Building and Construction said: “It is clear that more needs to be done to improve the consistency and accuracy of the Government’s construction pipeline. A stable pipeline would give the construction industry good visibility of future demand and the ability to plan and invest for that demand. It would lead to efficiencies for the Government and hence for the taxpayer. Instead we have a pipeline whose data is so incomplete, and which fluctuates so wildly and erratically that the industry can place no detailed reliance on it.  

“I hope that we will get a clearer picture in November when the Spending Review is published. But in the meantime the huge 28% drop in the number of projects included suggests some Government departments are putting projects on hold in the expectation that they get culled. I don’t expect we will see anything like the scale of cutback in capital programmes that the industry experienced in 2010, after the last election, but there is clearly cause for nervousness about the potential squeeze in spending.  

“I hope the Government will recognise that what this industry most needs is long-term certainty and stability in demand, to provide it with the confidence to invest in technology and its workforce. Our growing economy is creating a welcome uplift in private sector demand, but the Government should not use that as an excuse to cut back its own investments, create another hiatus, and send ripples of uncertainty through the industry.”

Featured News

Specification news
The country is not prepared for climate impacts, say...

There is now unequivocal evidence that climate change is making extreme weather in...

Read More >>

Specification news
New homes net zero transition plan

The new homes sector has set out its initial Transition Plan as a shared pathway and...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

AKW Bathroom Catalogue 2025 Brochure

AKW Bathroom Catalog...
By AKW

Download Now >>

Baths Collection Brochure Brochure

Baths Collection Bro...
By AKW

Download Now >>

Your high performance facade panel. With James Hardie, It’s Possible™ Brochure

Your high performanc...
By James Hardie

Download Now >>

James Hardie brings unique designs to life with beautiful fibre cement products that are built to last. It’s Possible™ Brochure

James Hardie brings...
By James Hardie

Download Now >>

fermacell® The Specification Guide Brochure

fermacell® The Speci...
By James Hardie

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

SOPRALENE FLAM 180 AF
SOPRALENE FLAM 180 AF

Membrane composed of elastomer modified bitumen and a non woven polyester reinforcement.The upper...

Read More >>

FLAGON SR DE PVC
FLAGON SR DE PVC

Membrane composed of flexible PVC and a polyester reinforcement. Available in different RAL...

Read More >>

FLAGON S PVC
FLAGON S PVC

Membrane composed of flexible PVC. Available in different RAL Colours.Used for detailing work. The...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Specification Insights with Majestic London Showers
Specification Insights with Majestic London Showers

Specification Insights with Majestic London Showers

Watch Now >>

Discover the first-ever reference book for stone wool insulated sandwich panels
Discover the first-ever reference book for stone wool insulated sandwich panels

“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...

Watch Now >>

Portakabin | Installation at the iconic Admiralty Arch, London
Portakabin | Installation at the iconic Admiralty Arch, London

Portakabin | Installation at the iconic Admiralty Arch, London

Watch Now >>