Delivering major projects in government

Public Sector Wed, Mar 23, 2016 9:19 AM

Delivering major projects in government

The National Audit Office has published a progress report on measures to improve the delivery of major government projects.

These include major service reforms, ICT projects and infrastructure and construction projects.

There have been initiatives designed to improve the oversight and delivery of projects but their impact is unclear, and it is of particular concern that a third of projects due to deliver in the next five years are rated as being in doubt or unachievable if action is not taken to improve delivery.

There are 149 projects in the Government Major Project Portfolio (the Portfolio), with a combined whole-life cost of £511 billion and an expected spend of £25 billion in 2015-16. These projects require Treasury approval based on their size, risk and impact. The public sector as a whole delivers many more projects outside the Portfolio, for example, through arm’s length bodies and other bodies such as Network Rail.

The public sector has had a poor track record in delivering projects successfully. While in the last Parliament, the NAO reported on improvements in the way aspects of programmes in some departments were managed, we also reported regularly on project failures and on ongoing projects that were experiencing considerable difficulties. Key recurring issues included an absence of portfolio management at both departmental and government level; lack of clear, consistent data with which to measure performance; poor early planning; lack of capacity and capability to undertake a growing number of projects; and a lack of clear accountability for leadership of a project.

The Infrastructure and Projects Authority (the former Major Projects Authority) and departments have taken many positive steps to develop capability and provide greater assurance on improving project delivery.  However, it is difficult to tell whether performance is improving without reliable and consistent measures of project success. Despite some improvements in the level of information published on major projects, there are still a number of issues which make it difficult to form conclusions about trends in performance. These include the amount of project turnover in the Portfolio; the limited data published by departments; inconsistent reporting of costs; and no systematic monitoring of whether the intended benefits have been achieved.

Delivery confidence shows a mixed picture with high risks to delivery in the next five years. The number of projects where successful delivery was in doubt or unachievable unless action was taken (rated red and amber-red) has increased since 2012 as more risky projects have entered the Portfolio. Uncertainty should reduce through the project lifecycle but not all project ratings improve over time. Of 56 projects which remained on the Portfolio from 2012 to 2015, 17 had red or amber-red ratings in June 2015 compared with 12 in 2012, although the number of projects considered highly likely to deliver on time and on budget (rated green or amber-green) also increased from 16 in 2012 to 25 in 2015.

It is particularly worrying that a third of projects (37 out of 106) due to deliver in the next five years are rated as red or amber-red.  Nearly 80 per cent of the Portfolio projects due to be delivered by 2019-20 are to either transform or change the way that services are delivered or accessed. Transformation programmes can present the greatest risk of failure and there is a need to balance ambition and realism in setting goals. For instance, the Better Care Fund was a challenging initiative which Ministers paused and redesigned after the early planning and preparations did not match its scale of ambition.

Progress in improving portfolio management is disappointing with no single organisation having a view of the whole portfolio of government projects. The Portfolio provides increased assurance, and other central departments have an increased role in assuring, approving and improving quality of delivery. But an effective mechanism still needs to be developed for prioritising projects across government or judging whether individual departments have the capacity and capability to deliver them. The NAO has often reported on the difficulties caused for government projects by unrealistic expectations and over-optimism.

Amyas Morse, head of the National Audit Office, said: “I acknowledge that a number of positive steps have been taken by the Authority and client departments. At the same time, I am concerned that a third of projects monitored by the Authority are red or amber-red and the overall picture of progress on project performance is opaque. More effort is needed if the success rate of project delivery is to improve."

Featured News

Specification news
Harmer SML below-ground drainage - cast-iron solutions...

Harmer SML Below-Ground Drainage is a trusted soil and waste system from Alumasc...

Read More >>

Specification news
Reynaers eases specification of access controls with...

As part of Reynaers’ suite of digital solutions, the Access Control Configurator...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

2026 Product Brochure Brochure

2026 Product Brochur...
By ​The Radiator Compan...

Download Now >>

System for Laying Floor and Wall Coverings Brochure

System for Laying Fl...
By FassaFloor

Download Now >>

Training for Excellence Brochure

Training for Excelle...
By Aico

Download Now >>

The Connected Home Solution Brochure

The Connected Home S...
By Aico

Download Now >>

Safety First, Aico First Brochure

Safety First, Aico F...
By Aico

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Glass Partition Walls
Glass Partition Walls

Partition wall systems made of glass allow transparent room partition. They open, divide and...

Read More >>

FASSAFILL MEDIUM
FASSAFILL MEDIUM

Water repellent cement-based sealant for grouting joints from 2 to 12 mm, resistant to mould and...

Read More >>

FASSA AQUAZIP FAST
FASSA AQUAZIP FAST

Two-component elastic cement membrane, quick drying even at low temperatures, for waterproofing and...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

DAB EsyBox Pop | Compact booster pump for perfect home water pressure
DAB EsyBox Pop | Compact booster pump for perfect home water pressure

Struggling with weak showers and inconsistent flow? The DAB EsyBox Pop is the revolutionary,...

Watch Now >>

Marsh Industries - Phos-Lite
Marsh Industries - Phos-Lite

Marsh Industries - Phos-Lite

Watch Now >>

Marsh Industries - Nutra-Lite
Marsh Industries - Nutra-Lite

Marsh Industries - Nutra-Lite

Watch Now >>