OFF-SITE CONSTRUCTION REDUCES PROGRAMME TIME FOR MAJOR NEW HOSPITAL BUILDING IN COLCHESTER BY AROUND 6 MONTHS

Latest News Tue, Mar 22, 2016 4:57 PM

OFF-SITE CONSTRUCTION REDUCES PROGRAMME TIME FOR MAJOR NEW HOSPITAL BUILDING IN COLCHESTER BY AROUND 6 MONTHS

ProCure21 partner, Kier Eastern, working with off-site specialist Yorkon, has reduced the programme for a major new hospital building at Colchester General Hospital by around six months.

Kier was Principal Supply Chain Partner appointed by Colchester Hospital University NHS Foundation Trust under the ProCure21 framework to provide the new facility as part of a £20m contract – the biggest development in the hospital’s recent history. The building was manufactured and fitted out off site and installed by Yorkon in a £10m sub-contract, reducing time on site to just 10 months.

Designed by Tangram Architects, the scheme increased the Trust’s capacity in time for the peak winter period.  It accommodates a new children’s department on the ground floor and an elective care centre and surgical ward on the upper floor, with plant rooms above.

In order to reduce the construction programme for the new building to the benefit of patient care, Kier and the Trust took the decision to use an off-site solution.  The approach also allowed an existing ward building on the site to remain in use until just days before the second phase of modules arrived on site. 

The new purpose-designed facilities include 68 inpatient beds, consultation and treatment rooms, nurses’ stations, two isolation beds, administrative offices, a school room, children’s dining room, utility room, stores, toilets and ancillary rooms.

Nick Chatten, Director of Corporate Development at Colchester Hospital University NHS Foundation Trust, said, “This project is the first phase in a programme of redevelopment at Colchester General Hospital.  Speed was the principal reason for using an off-site solution for the building.  We needed to have the new facilities operational in time for the busy winter period.”         

“The finished building is very impressive.  It provides a good patient environment for both children in the children’s department and adults in the elective care centre and the new surgical ward.  It addresses the issues of patient privacy and dignity, and we are pleased with the ambience, feel, space and quiet.  The scheme is also now helping us to provide additional capacity elsewhere in the hospital to deal with unexpected pressures.”

“Located near the main entrance, the building creates a strong image for the hospital with its striking architectural lines.  And most importantly, it has been well received by patients and staff.”

Commenting on the use of off-site construction, Nick Bache, Director at Kier Eastern, said, “A team from Kier visited the Yorkon production centre and one of their completed projects at the outset, and were impressed with the quality and approach.  Off-site construction has provided us with a fast-track site solution, safer working conditions and a considerable reduction in waste sent to landfill.”

“The logistics of the project, particularly for the two module delivery phases, required careful planning between the Trust, Kier and Yorkon, and I am pleased to report, it went very well.  We are very pleased with the finished building.”             

David Johnson, Director and General Manager of Yorkon, said, “This is one of the most challenging healthcare projects we have undertaken to date.  The shape of the site demanded a very complex modular layout, this is a highly constrained site, and there was only a short window for construction.”

148 steel-framed modules up to 14m long and 3.3m wide, and each weighing up to 12 tonnes, were delivered and installed in just 17 days.  The units were partially fitted out off site, including internal partitioning and first fix M&E services.

The building, which has achieved a BREEAM ‘very good’ rating (targeted), has created an attractive and welcoming environment for staff and patients, particularly given its prominent location next to the hospital’s main entrance.  It has deeply articulated façades finished in a palette of materials, including white render, vertical bands of rainscreen cladding and curtain walling.                                        

The new Yorkon pre-installed concrete floor has been used throughout – the first time this award-winning modular technology has been used for a complete building.  It is an innovative off-site solution ideal for high traffic areas and to accommodate sensitive hospital equipment.

The children’s department is arranged around two large central courtyards that provide a protected play area and a sensory garden. Internally it features multi-coloured and patterned flooring, walls in bright colours, murals and a distinctive design for the reception and nurses’ station, which as well as creating a cheerful interior, assists in way finding.

www.kier.co.uk            www.yorkon.info

Featured News

Specification news
Safe and secure fixing for PV with Kingspan PowerPlus

A Kingspan roof system obtains FM4478 testing. With the huge increase in...

Read More >>

Specification news
YY London, 30 South Colonnade

Full Structural Refurbishment of Original Canary Wharf OfficeCanary Wharf’s 30...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Novantica - Cement Free Restoration  Brochure

Novantica - Cement F...
By Fassa Bortolo

Download Now >>

Fassatherm System - Product Catalogue  Brochure

Fassatherm System -...
By Fassa Bortolo

Download Now >>

Fassarend System - Product Catalogue  Brochure

Fassarend System - P...
By Fassa Bortolo

Download Now >>

Fassalime System - Product Catalogue  Brochure

Fassalime System - P...
By Fassa Bortolo

Download Now >>

Sport England’s Performance Archery Centre Brochure

Sport England’s Perf...
By Passivent

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Straightcurve®
Straightcurve®

Straightcurve® – headquartered in Australia, is renowned for high-end innovative garden edging,...

Read More >>

RLG600 Access Flooring System
RLG600 Access Flooring System

The Kingspan RLG600 raised access floor panel is intended for light office use and is capable of...

Read More >>

RHG600 Simploc
RHG600 Simploc

Kingspan RHG600 Simploc is the heavy grade floor system, capable of handling up to a 12kN/m2...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Discover the first-ever reference book for stone wool insulated sandwich panels
Discover the first-ever reference book for stone wool insulated sandwich panels

“Building with stone wool insulated sandwich panels” written by Professor Imperadori, is now...

Watch Now >>

Portakabin | Installation at the iconic Admiralty Arch, London
Portakabin | Installation at the iconic Admiralty Arch, London

Portakabin | Installation at the iconic Admiralty Arch, London

Watch Now >>