Balfour Beatty Ground Engineering nears completion on piling for viaduct

Latest News Tue, Mar 22, 2016 5:25 PM

Balfour Beatty Ground Engineering nears completion on piling for viaduct

Balfour Beatty Ground Engineering, (BBGE) is nearing completion of the piling phase for the new Reading viaduct, part of Network Rail’s Reading station area redevelopment.  

The new £40 million viaduct, being constructed by Balfour Beatty, will ease congestion by taking fast mainline trains over freight and relief lines.

The £3.8 million foundations package commenced in May and includes the installation of 980 continuous flight auger piles to support the viaduct structure. The ground improvement phase to install 1685 vibro concrete columns, to support the ramps at the Eastern and Western ends, also being carried out by BBGE, will commence in November.

Working alongside the live railway, safety and logistics have been key to planning the project.  One of the most critical stages was the installation of piles neighbouring the trackline on the main London to Swansea main line and Reading commuter routes. These created a pinch point which required careful planning to accommodate rigs and handling cranes in such a restricted area.

Balfour Beatty Ground Engineering Project Manager, Rob Cannon, said: “Careful planning was essential to this project, and our use of lean visual management has enabled us to closely monitor and control activities as well as provide instant updates to Network Rail.”

Jim Weeden, Network Rail, Reading Station and Area Redevelopment Acting Project Director, said: “Over 20,000 linear metres of piling has been completed by the Balfour Beatty Ground Engineering piling crews. 

"The fact that all of it has been successfully completed within 15 metres of the operational railway, without any impact on train operations or driver concerns is a major contribution to the satisfaction of passengers on this key route.”

Featured News

Specification news
Fassa Bortolo – Training, Innovation and Support for...

At Fassa Bortolo, we believe that knowledge is just as important as materials when it...

Read More >>

Specification news
More than £1bn of major projects at tender stage

More than £1 billion-worth of contracts on major projects are at the tender stage...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

ACO Blue Roof Guide – Vol 2 Brochure

ACO Blue Roof Guide...
By ACO Building Drainag...

Download Now >>

Stannah Commercial Brochure Brochure

Stannah Commercial B...
By Stannah Group

Download Now >>

Stannah Midilift CLS Brochure

Stannah Midilift CLS
By Stannah Group

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

AlarmCalm
AlarmCalm

OverviewAlarmCalm is a powerful, flexible false fire alarm management solution that’s simple to...

Read More >>

QuickZone
QuickZone

OverviewQuickZone is our fuss-free conventional fire panel range.Quick to fit, configure and...

Read More >>

ExGo
ExGo

OverviewExGo provides a simple, dependable solution to complex fire protection problems in high-risk...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

The UK's No 1 Pool, Spa and Wellness Show – SPATEX 30 secs
The UK's No 1 Pool, Spa and Wellness Show – SPATEX 30 secs

And there’s a chance to do it all over again when the BIG 30th anniversary edition of SPATEX 2026...

Watch Now >>

Reclaimed Brick Company Leah's Yard Square Sheffield
Reclaimed Brick Company Leah's Yard Square Sheffield

Reclaimed Brick Company is part of Leah's Yard Square in Sheffield, a historic site revitalised for...

Watch Now >>

Day in the life of a Reclamation Yard
Day in the life of a Reclamation Yard

A typical day at a reclamation yard is filled with activity and discovery. Early mornings often...

Watch Now >>