Balfour Beatty recently completed the upgrade of the Garroch roundabout on the A75 in Dumfries, seven weeks ahead of schedule.
The works are a key milestone on the programme to enable construction of the new £230m Dumfries and Galloway district general hospital to start at the Garroch site.
Balfour Beatty was responsible for the £1.2m project to reconfigure the roundabout which is required to ensure traffic in and out of the new 350-bed hospital complex is effectively managed, while keeping traffic moving along this key route.
The works included increasing the size of the existing four-leg roundabout, relocating one leg of the roundabout to accommodate access to the new hospital and the existing side road, realigning the remaining approach roads and other works associated with a trunk road scheme.
Transport Minister Keith Brown welcomed the news that the contract was completed seven weeks ahead of schedule and on budget.
Keith Brown said: “Good access for local communities to the new hospital facilities in Dumfries and Galloway will be an essential part of the new health complex. It is important that traffic visiting the new Infirmary, where construction starts next year, is managed well and the upgraded roundabout at Garroch will ensure better managed traffic in and out of the new infirmary.”
Dennis O’Keeffe, Project Director for the new hospital in NHS Dumfries and Galloway said: “We are delighted that the works have been completed ahead of programme with minimal disruption to the travelling public and local community. Balfour Beatty has effectively planned, communicated and implemented traffic arrangements and its approach to the delivery of this complicated contract has been exemplary. We can now concentrate our efforts on the reprovision of the hospital, with construction works due to start in spring 2015.”
Hector MacAulay, Balfour Beatty Delivery Unit Managing Director, said: “The focus of Transport Scotland, NHS Dumfries and Galloway and our project team was always to undertake the reconfiguration of the Garroch roundabout, which is on the strategic trunk route through the region, with minimal disruption.
"By working together, carrying out as much work as possible offline during the day and works within the traffic management at night, we were able to successfully complete the upgrade almost two months early. We would like to thank the public for their cooperation and patience during the construction period.”
Featured News
One of the stunning Hunter Douglas solid wood grill ceiling and wall systems has...
As extreme weather events are projected to become more frequent due to climate...
BUILDING PRODUCT LIBRARY - LATEST BROCHURES
HPS200 Ultra Case St...
By Tata Steel
Confidex Datasheet
By Tata Steel
Prisma UK 2024
By Tata Steel
HPS200 Ultra UK
By Tata Steel
Amtico Bio Support D...
By Amtico
BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS
Offers the most comprehensive guarantee for pre-finished steel products in Europe and provides peace...
Colorcoat HPS200 Ultra®Super durable guaranteed performance.Designed to withstand even the most...
Colorcoat Prisma®Aesthetics that last, guaranteed.Colorcoat Prisma® demonstrates a step change by...
CONSTRUCTION VIDEOS - LATEST VIDEOS
Mira Showers is delighted to introduce the new Mira Vista HeatloopTM – an innovative and stylish...
https://www.aandslandscape.co.uk/ Find out why A&S Landscape Canopies last longer than alternatives....
A&S Landscape designed and installed a large enclosed, curved roof canopy for Hampton Gardens School...