Layher systems central to iconic building refurbishment

Regeneration Tue, Mar 22, 2016 5:36 PM

Layher systems central to iconic building refurbishment

A major Layher Keder XL temporary roof structure – the largest to date in Europe – has been installed for a prestigious refurbishment project at the University of Cambridge.  

The roofing system, together with Layher’s Allround access and support scaffolding, was built by Connect Scaffolding for main contractor Kier Construction as part of the extensive upgrade work being undertaken on the ARUP Building Museum of Zoology.

“The installation has presented specific challenges, which have been met by close co-operation between Layher’s and Connect’s design teams and which have also been addressed by the Layher roof and scaffolding designs,” says Oliver Cave, Managing Director of Connect Scaffolding.  

“These include space and location considerations – there being no crane access possible – and the fact that the surrounding buildings and thoroughfares remained occupied and used throughout.”  

Layher Allround has been erected around the structure to a total of 12 lifts and an overall height of some 30 metres with buttress support scaffold used at key points – no physical anchors being permitted to the majority of the building fabric.  

“The ‘brutalism’ architectural style, for which the ARUP Building is well known, features a series of step-ins and cantilevered elements, which had to be accommodated by the scaffolding design,” continues Oliver Cave.  “Thus walkways of varying depths are incorporated, which still gain from the absence of cross-bracing that is a characteristic of the Layher scaffolding design.”

Because the Allround system is built from lightweight materials and features built-in rosette connectors, the number of components is minimised – a significant benefit in terms of safety, particularly in such an occupied location.

“This is also an important factor with the Keder temporary roof because the entire structure had to be assembled by hand from a wide-stepped gable,” adds Simon Lewis, Senior Design Engineer at Layher.  

“Roof truss components were raised by one of three Geda Hoists and fixed in position at one gable end, before being rolled out on nylon wheels set on a scaffolding track to create space for the next truss to be assembled.  Once fully installed, the Keder XL sheeting was then pulled across the roof one bay at a time to complete the structure with the result providing protection from the weather and a naturally-lit working environment.”  

Simon Lewis also highlights the innovative design of specialised tie transfer beams and tie collars, which have been used specifically to tie the roof system to the RC columns every 11 metres.

The versatility of the Layher Allround system is further demonstrated by the fact that, in selected areas, it is built off steelwork that was also installed by Connect Scaffold as a primary support.  This was undertaken as an additional safety measure relating to the location.  

The project also incorporated access for extensive internal works, including a crash deck, which can be readily adjusted as the project proceeds.

“This is an excellent demonstration of the suitability of our Allround scaffolding and Keder XL temporary roofing systems being used – both for a highly prestigious project and also in an area where access and operational considerations need to be accommodated,” adds Sean Pike, MD at Layher UK.

“It is a high quality installation for an iconic 1960s’ building of significant importance – the zoology museum, for example, houses many of Darwin’s specimens – and we are delighted to have been involved at such an important and well regarded location.”

Featured News

Specification news
Abloy UK and Knightsbridge Security Systems provide...

Abloy UK and Knightsbridge Security Systems have supplied luxury car dealer H.R. Owen...

Read More >>

Specification news
Speedy and sustainable refurbishments with Forbo’s...

With a focus on delivering flooring solutions that provide significant reductions in...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

Vertical radiators complete range Brochure

Vertical radiators c...
By Myson

Download Now >>

Myson Radiant Heating Premium underfloor heating systems Brochure

Myson Radiant Heatin...
By Myson

Download Now >>

Which heat emitter is the right one? Brochure

Which heat emitter i...
By Myson

Download Now >>

Sustainable heating solutions for renovation Brochure

Sustainable heating...
By Myson

Download Now >>

Rearo Tradeline Brochure

Rearo Tradeline
By Rearo

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

DUOFLEX
DUOFLEX

DUOFLEX is a high quality elastomeric bitumen, hot bonded to the substrate incorporating the fleece...

Read More >>

TECSOUND
TECSOUND

TECSOUND is a polymer based, bitumen-free, high-density synthetic membrane. The combination of its...

Read More >>

ISOLAIR MULTI
ISOLAIR MULTI

ISOLAIR MULTI is a natural and ecological vapour-permeable, windproof and water-repellent thermal...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Our SUSTAINABILITY Roadmap
Our SUSTAINABILITY Roadmap

Myson has a clear sustainability strategy in line with the UN Sustainable Development Goals (SDGs)...

Watch Now >>

Sustainable Energy Efficient Solutions
Sustainable Energy Efficient Solutions

From radiators and underfloor heating to ceiling convectors and towel warmers, Myson is the UK’s...

Watch Now >>

UNISENZA PLUS Smart Controls_The complete system solution
UNISENZA PLUS Smart Controls_The complete system solution

With Unisenza Plus Smart Controls you can easily monitor and control all linked heating products via...

Watch Now >>