New hospitals further delayed by Carillion collapse

Latest News Fri, Jan 17, 2020 8:21 AM

The two PFI (Private Finance Initiative) hospitals that Carillion was building at the time it collapsed - Royal Liverpool University Hospital and Midland Metropolitan Hospital - are currently due for completion several years late.

However, the government has ensured that most of the increased construction costs so far have been borne by the private PFI investors and Carillion, rather than the taxpayer, according to a new investigation by the National Audit Office (NAO).

The NAO’s report finds that the 646-bed Royal Liverpool, which was due to open in June 2017, is now forecast to be completed more than five years late, in the autumn of 2022, and the Liverpool University Hospitals NHS Foundation Trust has not yet set an opening date. It is now predicted to cost a total of £1,063 million to build and run compared to the original £746 million.2 The taxpayer is currently expected to pay £739 million of this, a reduction of 1% from what was originally planned.

The 669-bed Midland Metropolitan, which was originally due to open in October 2018, is now expected to open in July 2022. The hospital is due to cost at least £988 million in total to build and run - over £300 million more than the original £686 million.3The taxpayer is currently expected to pay £709 million of this, an increase of 3% from what was originally planned.

The private sector has borne most of the cost increase: shareholders, investors, insurers and Carillion have lost at least £603 million on the construction of both projects. The government wanted to ensure the private sector honoured its contracts and rejected proposals that it should provide more public funding to ‘bail out’ the PFI schemes or reduce the risk that lenders were exposed to.

Unite, the UK and Ireland’s largest union, says the report highlights the government failures to get the two flagship Carillion hospitals built, creating misery for patients and staff forced to cope with failing buildings.

Some of the delay was a result of the government being initially still wedded to completing both projects under the Private Finance Initiative (PFI). However the problems were so great that not only could PFI not be used for the two hospitals but the government has scrapped in its entirety.

The report does highlight that the government wrongly paid £42 million in compensation to the private investors on the Royal Liverpool. If it had delayed paying the compensation until it was fully aware of the cost of the project to complete, the money could have been saved.

Unite assistant general secretary Gail Cartmail said: “The report makes for grim reading and endorses what hospital patients and NHS staff in Liverpool and the West Midlands already knew.

“Two desperately needed hospitals are going to be years late and in the meantime local communities are left with facilities that are no longer fit for purpose.

“The responsibility for these delays has to lie squarely at the door of the government, which consistently failed to prioritise the overriding need that these hospitals had to be built.

“While the report notes the financial cost of the projects the human cost of the delays of completing the hospitals has not been recognised.”

The NAO reveals that there were significant construction problems and delays before Carillion went into liquidation on 15 January 2018 but the contractor’s collapse created more delay. Work on both sites stopped while the hospital Trusts, government and the private investors attempted to rescue the projects. By September 2018, these attempts had failed; government decided to terminate the PFI schemes and provide public financing to complete the hospitals. It has then taken time to put in place new contracts and restart the projects.

The full extent of construction problems at Royal Liverpool began to emerge after Carillion collapsed and over the course of 2018. The new construction contractor has had to strip out three floors of the building and start major work to reinforce the structure with steelwork and additional reinforced concrete.

The Department of Health & Social Care (DHSC) paid £42 million compensation to Royal Liverpool’s investors to terminate the PFI contract. The contract required the Trust to pay compensation to the PFI company’s lenders, based largely on the estimated cost to complete the hospital, before the actual cost to complete the hospital was known. Had the Department and Trust better understood the cost to complete the hospital, they may not have paid anything to the lenders. The estimated cost of completing the hospital has risen from £117 million in September 2018, when DHSC agreed the termination payment, to £293 million now.

The new suppliers for both the Trusts were chosen without competition. After the termination of the PFI contract, in order to restart the Liverpool project without further delay, the Liverpool Trust agreed contracts with several new suppliers without a public procurement process. The Sandwell and West Birmingham Hospitals NHS Trust ran a public procurement for the contract to complete Midland Metropolitan taking 15 months, which only attracted one viable bidder.

There are significant risks of further delays and added costs at the hospitals, although their situations are different. Both Trusts are now directly managing the contracts with new construction firms.

At Midland Metropolitan, the Sandwell Trust has negotiated a ‘target price’ for work by its new contractor, Balfour Beatty, and prices should not rise unless the Trust changes the scope of the project or there are unforeseen problems with Carillion’s work.

At Royal Liverpool, the new main contractor, Laing O’Rourke, has no contractual incentives to control costs. NHS England and NHS Improvement has worked with the Liverpool Trust to develop additional oversight arrangements such as using an independent construction consultancy to advise on the appropriateness of costs.

Featured News

Specification news
Social homes are 14% less energy efficient

A new study has revealed that the average energy efficiency rating for social housing...

Read More >>

Specification news
The 2024 Civic Trust Awards winners

The Civic Trust Awards proudly celebrated its 65th Anniversary with the Awards...

Read More >>

BUILDING PRODUCT LIBRARY - LATEST BROCHURES

REVO.Prime TSA 325 NT Brochure

REVO.Prime TSA 325 N...
By GEZE UK Ltd

Download Now >>

Natural ventilation strategy for Sunderland SEND school Brochure

Natural ventilation...
By Passivent

Download Now >>

Squash Court Flooring Brochure

Squash Court Floorin...
By Junckers Limited

Download Now >>

Junckers Acoustics Floor System Brochure

Junckers Acoustics F...
By Junckers Limited

Download Now >>

BUILDING PRODUCT DIRECTORY - LATEST PRODUCTS

Ei1025 Environmental Sensor
Ei1025 Environmental Sensor

Discreet and secure, the Ei1025 Environmental Sensor can be placed throughout a property to monitor...

Read More >>

Ei1000G SmartLINK Gateway
Ei1000G SmartLINK Gateway

The Gateway and Cloud portal use Aico’s SmartLINK technology to bring together data from all...

Read More >>

Ei3030 Multi-Sensor Fire and Carbon Monoxide Alarm
Ei3030 Multi-Sensor Fire and Carbon Monoxide Alarm

The Ei3030 is a multi-sensor Fire & Carbon Monoxide (CO) Alarm. Containing our proven and dependable...

Read More >>

CONSTRUCTION VIDEOS - LATEST VIDEOS

Forma aluminium column casings for Winchester College
Forma aluminium column casings for Winchester College

In progressive and dynamic business sectors, such as construction, it’s natural to be forward...

Watch Now >>

Decorative metal bulkheads & column casings for Tesco Extra, Birmingham
Decorative metal bulkheads & column casings for Tesco Extra, Birmingham

Decorative aluminium horizontal bulkheads more than 100 metres long have been supplied and installed...

Watch Now >>

Vecta building linings for the perfect finish
Vecta building linings for the perfect finish

More than 150 sq.m of Vecta aluminium wall lining and a feature bulkhead have been manufactured and...

Watch Now >>